Templates/Drywall

Free Drywall Estimate Template

A complete, line-item drywall estimate you can preview below — 1/2in and 5/8in board, hang, tape and three-coat mud, corner bead, texture, sanding and cleanup — plus a plain-language code checklist covering fire-rated assemblies, water-resistant board and fastener spacing.

Estimate #DW-2026-061
Nguyen Residence — Basement Finish
3,200 sq ft board · Level 4 finish · knockdown ceiling texture
Sample
Line itemQtyAmount
1/2" gypsum board — walls2,400 sf$1,152.00
5/8" Type X board — garage ceiling480 sf$312.00
Moisture-resistant board — bath320 sf$243.00
Hang labor3,200 sf$1,280.00
Tape & 3-coat mud (Level 4)3,200 sf$1,760.00
Corner bead & trims260 lf$390.00
Knockdown texture — ceilings980 sf$588.00
Sanding, cleanup & debris haul1 lot$420.00
Total$6,145.00

Payment schedule

Deposit (on approval) (30%)$1,843.50
Board hung & inspected (40%)$2,458.00
Final — finish, texture & cleanup (30%)$1,843.50

How to measure and price drywall work

  • Measure total board square footage (walls + ceilings), then divide by 32 for 4x8 sheets or 48 for 4x12 sheets and add 10% waste.
  • Price hang and finish separately — hang is usually $0.35–0.55/sf and tape/finish $0.45–0.75/sf depending on finish level.
  • Add linear-foot lines for corner bead and a per-square-foot line for texture; disposal is always its own item.

Drywall building-code guide

2021 IRC Chapter 7 (R702.3) and GA-216 — gypsum board application and finishing

Drywall inspections focus on where fire-rated or water-resistant board is required, how the board is fastened, and whether the finish level matches what the job called for.

FIRE SEPARATION (IRC R302.6)
  • Garage-to-house separation requires minimum 1/2" gypsum on the garage side; 5/8" Type X on ceilings under habitable rooms
  • Garage walls supporting a habitable space above must be protected on the garage side floor to ceiling
  • Penetrations through a rated assembly must be firestopped with an approved material — spray foam is not automatically approved
WET AREAS (IRC R702.3.8 / R702.4)
  • Regular paper-faced gypsum is NOT allowed as a tile backer in tub or shower areas — use cement board, fiber-cement or a listed water-resistant backer
  • Water-resistant "green board" may be used on bathroom walls outside the direct shower area, but not on ceilings with framing over 12" o.c.
  • Vapor retarders behind tile backer must follow the manufacturer's system — do not double up impermeable layers
FASTENING & SPACING (IRC Table R702.3.5)
  • Screws: 16" o.c. on ceilings and 16" o.c. on walls for 1/2" board over 16" o.c. framing (12" for ceilings with heavy texture)
  • Fastener heads must be dimpled just below the paper without breaking it — broken paper means no holding power
  • Keep board edges 1/4" off the floor and stagger end joints so no four corners meet
FINISH LEVELS (GA-214)
  • Level 3 — for heavy texture or wall coverings; Level 4 — the standard for flat or eggshell paint
  • Level 5 (skim coat) is required for gloss paint or critical raking light; always price it as a separate line
  • Ceilings receiving flat paint under natural light almost always need Level 5 — get this in writing before you start

Code quick referenceDrywall

ItemRequirementCode reference
Board thickness1/2in walls, 5/8in ceilings at 24in framingIRC R702.3
Screw spacing12in OC ceilings, 16in OC wallsIRC Table R702.3.5
Garage separation1/2in gypsum on garage side, 5/8in Type X under habitable spaceIRC R302.6
Wet areasCement/fiber backer, not paper-faced gypsum in showersIRC R702.4
Finish levelLevel 4 for flat paint, Level 5 for gloss/critical lightGA-214

Drawings & details

Simplified section and plan views of the details inspectors look at most. Illustrative only — not to scale.

Fastener spacing
2 · 16.00" OC1 · 1.50"3 · 8' 0"4 · 8' 1 8/16"
Clearances, spacing & part thickness

Adjust the values — the drawing below updates in real time.

Drawing legend
  • 1 · Member thicknessScrews 12in OC on ceilings, 16in OC on walls(1.50")
  • 2 · On-center spacing16in OC framing(16.00" OC)
  • 3 · Member lengthPlate to plate(8' 0")
  • 4 · Overall runTotal covered by this layout(8' 1 8/16")
Client presentation summary
  • On-center spacing: 16.00" · 7 members
  • Overall run: 8' 1 8/16" · Member length: 8' 0"
  • Screws 12in OC on ceilings, 16in OC on walls
Type X 5/8in board where fire separation is required (garage/house, shafts).
Finish build-up
1 · Paint / texture — 0.06"2 · Third coat + sand — 12.00"feathered 12in+12.00"3 · Tape + two coats mud — 0.06"4 · Gypsum board on framing — 0.50"1/2in walls · 5/8in ceilings1' 0 10/16"Section view — top layer first · Total assembly: 12.63"
Clearances, spacing & part thickness

Adjust the values — the drawing below updates in real time.

Drawing legend
  • 1 · Paint / textureLayer in the assembly, drawn top to bottom(0.06")
  • 2 · Third coat + sandfeathered 12in+(12.00")
  • 3 · Tape + two coats mudLayer in the assembly, drawn top to bottom(0.06")
  • 4 · Gypsum board on framing1/2in walls · 5/8in ceilings(0.50")
Client presentation summary
  • Paint / texture: 0.06"
  • Third coat + sand: 12.00"
  • Tape + two coats mud: 0.06"
  • Gypsum board on framing: 0.50"
  • Total assembly: 12.63" (1' 0 10/16")
Level 4 finish for flat paint, Level 5 (skim coat) for gloss or raking light.
Inspection-day checklistShow
  • Fire-rated assemblies photographed before taping.
  • Screws set flush, not broken through the paper face.
  • Corner bead straight and fastened, no floating edges.
  • Backer board and membrane in wet areas before tile.
  • Board joints staggered and not landing on window/door corners.

Code references are based on the 2021 IRC and related model codes. Local amendments, state codes and manufacturer instructions can be stricter — always confirm with your local building department before starting work.

Common drywall estimating mistakes

  • Quoting a single $/sf number that hides the finish level, then getting asked for Level 5 at no extra charge.
  • Forgetting the 5/8in Type X upgrade on garage ceilings — it fails inspection and costs a full re-hang.
  • Not pricing sanding, dust protection and debris haul, which can be 10% of the job on an occupied remodel.
PDF & client share

Export a branded, client-ready PDF or send a sign-from-phone link.

Digital signature

Your client reviews and signs the estimate from any device.

Code-aware

IRC Chapter 7 guidance for fire-rated garage separation, wet-area backer board, fastener spacing and finish levels.

Drywall estimate FAQ

What should a drywall estimate include?

A drywall estimate should list board type and square footage, hang labor, tape and mud with the finish level, corner bead, texture, sanding and cleanup, plus a milestone payment schedule.

How much does drywall cost per square foot?

In most U.S. markets hang and finish runs $1.80–$3.00 per square foot of board installed, including materials. Level 5 finish, high ceilings and small patch work push the number higher.

What building codes apply to drywall?

IRC Chapter 7 (R702.3) governs gypsum board application and fastener spacing, R302.6 covers garage fire separation, and R702.4 restricts paper-faced board in wet areas.

Turn this template into your estimate

Free to start. Pro at $19/mo for unlimited estimates. No card required for the 14-day trial.